7 Line Extension, originally uploaded by plemeljr
First of Two Machines Will Drill 7,100-Foot Tunnels from 11th Avenue and 25th Street to Times Square:
today, a 100-ton tunnel boring machine (TBM) was lowered under 11th Avenue marking the start of excavation work for the 7 line subway extension project. The $2.1 billion project, funded by the City and managed by the MTA, will help transform the Hudson Yards vicinity into a vibrant 24-hour neighborhood, containing a mix of commercial, residential, retail, open space and recreational uses.
…
The piece of the TBM lowered today near the intersection of 25th Street and 11th Avenue, known as the “cutter head,” has forty-four rotating discs that will drill a tunnel to Times Square. During the project, two TBMs will excavate two, 7,100 foot-long tunnels.